Block 32 UAB

2017041241705-1920-1200
2017041241703-1920-1200
2017041241708-1920-1200
2017041241710-1920-1200
2017041241713-1920-1200
2017041241716-1920-1200
2017041241718-1920-1200
2017041241720-1920-1200
2017041242404-1920-1200
2017041242416-1920-1200
2017041241705-1920-1200
2017041241703-1920-1200
2017041241708-1920-1200
2017041241710-1920-1200
2017041241713-1920-1200
2017041241716-1920-1200
2017041241718-1920-1200
2017041241720-1920-1200
2017041242404-1920-1200
2017041242416-1920-1200

Project details

  • Location: Ft. Collins
  • Project Type: Decorative/Architectural
  • Project Timeline: 22 months
  • Project Size: 3 Story - 37,500sqft
  • Concrete: 2,000cy
  • Architect: RNL Design
  • Structural Engineer: JVA, Incorporated
  • General Contractor: Adolfson & Peterson
  • Concrete: Three Brothers Concrete

The Utilities Administration Building (UAB) a three-story 37,500 sqft structure is located at the northeast corner of Laporte Ave. and N. Howes St. in Old Town Fort Collins was designed by Denver’s RNL Design. The $14.1 million building serves as a model of energy efficiency through the treatment of windows, walls and internal systems. It is connected to the electric utility’s grid, but it also generates and stores energy through the use of solar panels, batteries and a direct-current electrical system making it become one of the country’s most energy-efficient buildings. The site also includes the restored landmark Butterfly Building which was moved 100 feet to the east to make room for the new administration building. The Block 32 project is part of the City of Fort Collins’ downtown Civic Center master plan, and achieved a LEED Platinum certification.

 

The City’s Arts in Public Places program was used to place several pieces of art created from local artists in and throughout the building. These include a sculpture of the Poudre River as part of the entryway column, and Colorado’s first outdoor perennial living wall. Specially designed walls on the ramps and steps at the front of the building represent the different departments for the City – light/power, water, etc.

 

Project Challenges:

The required City’s Art in Public Places program called for A&P and Bestway to work with a local artist to create a functional structural retaining wall. This wall would also need to allow for an intricate relief panel to be transferred into the concrete. There were many small tight corners and edges in the artists design and the team would only get one chance to get it right for this cast-in place artistic retaining wall. This was also made more difficult by the lack of ability to vibrate the front face of the retaining wall, due to the amount of bracing needed.

 

Project Solutions:

Bestway meet several times with A&P and the artist as we devised a plane for a concrete flowable enough to get into all the crevices of the intricate design, but also needed to be strong enough to hold back the forces of the ground behind it. Using a traditional Self-Consolidating Concrete (SCC) was not possible on this project, because of the increasing hydro-static pressure along the wall as the entire retaining wall. Due to the artistic design the wall needed to be placed at one time to keep the flow of the design. Bestway provided several options for maximizing the flowability, without increasing the pressures. We did several mock-up pours to work out the fine details of the mix and to assure A&P had enough bracing to support the weight. In the end, the artwork came out excellent and is a central focus for the entrance of the building. This project also used an array of colors, including Green concrete, which adds to the pleasing aesthetic to the front of the building.